タイトルError Cost Escalation Through the Project Life Cycle
本文(外部サイト)http://hdl.handle.net/2060/20100036670
著者(英)Dick, Brandon; Haskins, Bill; Moroney, Gregory; Stecklein, Jonette M.; Dabney, Jim; Lovell, Randy
著者所属(英)NASA Johnson Space Center
発行日2004-06-19
言語eng
内容記述It is well known that the costs to fix errors increase as the project matures, but how fast do those costs build? A study was performed to determine the relative cost of fixing errors discovered during various phases of a project life cycle. This study used three approaches to determine the relative costs: the bottom-up cost method, the total cost breakdown method, and the top-down hypothetical project method. The approaches and results described in this paper presume development of a hardware/software system having project characteristics similar to those used in the development of a large, complex spacecraft, a military aircraft, or a small communications satellite. The results show the degree to which costs escalate, as errors are discovered and fixed at later and later phases in the project life cycle. If the cost of fixing a requirements error discovered during the requirements phase is defined to be 1 unit, the cost to fix that error if found during the design phase increases to 3 - 8 units; at the manufacturing/build phase, the cost to fix the error is 7 - 16 units; at the integration and test phase, the cost to fix the error becomes 21 - 78 units; and at the operations phase, the cost to fix the requirements error ranged from 29 units to more than 1500 units
NASA分類Economics and Cost Analysis
レポートNOJSC-CN-8435
権利Copyright, Distribution as joint owner in the copyright


このリポジトリに保管されているアイテムは、他に指定されている場合を除き、著作権により保護されています。