タイトル | Synthetic natural gas in California: When and why |
本文(外部サイト) | http://hdl.handle.net/2060/19790019444 |
著者(英) | Wood, W. B. |
著者所属(英) | Southern California Gas Co. |
発行日 | 1978-08-15 |
言語 | eng |
内容記述 | A coal gasification plant planned for northwestern New Mexico to produce 250 MMCFD of pipeline quality gas (SNG) using the German Lurgi process is discussed. The SNG will be commingled with natural gas in existing pipelines for delivery to southern California and the Midwest. Cost of the plant is figured at more than $1.4 billion in January 1978 dollars with a current inflation rate of $255,000 for each day of delay. Plant start-up is now scheduled for 1984. |
NASA分類 | PROPELLANTS AND FUELS |
レポートNO | 79N27615 |
権利 | No Copyright |
URI | https://repository.exst.jaxa.jp/dspace/handle/a-is/569069 |